Line Balance Efficiency Formula: Takt Time and Bottlenecks

Maintenance & QualityUpdated November 4, 202621 min read

A kaizen report from a Japanese plant lands on your desk. It shows a bar chart labeled 山積み表 (yamazumi-hyo), a "neck process," and a hensei koritsu of 76.9%. Meanwhile, your own team has added an operator to a struggling assembly line, and output has not moved at all.

Both situations come down to one rule: a flow line can only turn out products as fast as its slowest station. If one of five stations takes 52 seconds and the others take 30–44 seconds, the line still turns out one unit every 52 seconds. Adding people elsewhere only adds idle time at the other stations.

This guide explains takt time, cycle time, and the bottleneck, walks through the line balance efficiency formula with a worked example, and lays out a six-step improvement process. It also maps the Japanese terms you will see in reports from Japanese plants to their usual English names, and ends with a worksheet, a checklist, and questions to ask the Japanese side.

Contents
  1. What Is Line Balancing? The Slowest Station Sets the Pace
  2. Takt Time vs. Cycle Time vs. Bottleneck
  3. Line Balance Efficiency Formula (With a Worked Example)
  4. How to Improve Line Balance in Six Steps
  5. Fixing the Bottleneck: Four Options and ECRS
  6. Before and After: How the Numbers Change
  7. Common Mistakes and How to Avoid Them
  8. Line Balance Worksheet: Set It Up in Excel
  9. Checklist and Questions for the Japanese Side
  10. Limits of This Guide
  11. Summary
  12. FAQ
  13. Sources

What Is Line Balancing? The Slowest Station Sets the Pace

Line balance describes how evenly work time is spread across the stations of a flow line. The Japan Institute of Industrial Engineering (JIE), citing Japanese Industrial Standard JIS Z 8141, defines line balancing as a method for equalizing the workload assigned to each workstation on a production line.

A workstation is the position covered by one operator or one machine. Japanese shop floors usually just call it a kotei (工程, process), so a Japanese report may say "process 2" where you would say "station 2." This guide uses "station."

Take a five-station line where one station needs 52 seconds and the others need 30–44 seconds. The line produces only one unit every 52 seconds. The station before it waits to hand off work-in-process, and the station after it waits for parts to arrive.

Figure 1: Line Balance on a Yamazumi Chart

Plot each station's work time as a bar, and the bottleneck and the idle time stand out at a glance.

Takt time 45 s
38 s
52 s
30 s
44 s
36 s
Station 1Station 2
(bottleneck)
Station 3Station 4Station 5

Fictional example created for this article. Bar height is work time; the dashed line is takt time, set by customer demand. Station 2 takes 52 seconds, longer than takt, so the line cannot meet demand as it stands.

Japanese plants often call this bar chart a pitch diagram (ピッチダイアグラム) or a yamazumi-hyo (山積み表, "stacked-up chart"). In English, it is best known as a yamazumi chart, and it is the basic tool for seeing line balance. It needs only work time on the vertical axis and stations on the horizontal axis, so anyone can build one in Excel.

The gap between the tallest bar and each of the others is idle time, or te-machi (手待ち): time when an operator is waiting with nothing to do. Improving line balance means shrinking those gaps, with the goal of bringing every bar to just below the takt time line.

Japanese reports use several more terms for the same ideas. The table below lists the ones you are most likely to meet and the English names most engineers use.

Japanese termRomajiUsual English name
ラインバランス / ラインバランシング(loanword)Line balance / line balancing
編成効率 / 作業編成効率hensei koritsuLine balance efficiency
バランスロス率(loanword)Balance loss (balance delay)
ネック工程nekku koteiBottleneck station (the "neck" of the line)
タクトタイム / ピッチタイム(loanwords)Takt time
サイクルタイム(loanword)Cycle time
手待ちte-machiWaiting / idle time
山積み表 / ピッチダイアグラムyamazumi-hyoYamazumi chart
山積み・山崩しyamazumi / yamakuzushiStacking and leveling work (rebalancing)
要素作業yoso sagyoWork element
先行順位図senko jun'i-zuPrecedence diagram
標準手持ちhyojun temochiStandard in-process stock (standard WIP)
多能工tanokoMulti-skilled operator
混流ラインkonryu rainMixed-model line

One trap: in Japan, pitch time is just another name for takt time. In Western lean usage, "pitch" means something else: takt time multiplied by the pack-out quantity, such as the time to fill one container. If a Japanese document says "pitch time 45 s," read it as takt time.

Takt Time vs. Cycle Time vs. Bottleneck

Line balancing discussions mix several similar-sounding terms. Separating takt time, cycle time, and the bottleneck before doing any math makes everything that follows much easier.

Figure 2: Takt Time, Cycle Time, and Bottleneck Compared

Takt time is the target, cycle time is current performance, and the bottleneck is the ceiling for the whole line.

Takt time
Cycle time
Bottleneck
Meaning
Target pace: how many seconds per unit you need to meet customer demand
Time each station actually takes to complete one unit
The station with the longest cycle time
Set by
Available time ÷ required quantity (demand)
Work content, equipment, and operator skill
Comparing the cycle times of all stations
Example
27,000 s ÷ 600 units = 45 s
Station 1: 38 s; Station 2: 52 s
Station 2 (52 s)
Question it answers
How many do we need to make?
How long does each station take?
How often can the line turn out a unit?

Japanese plants also call takt time "pitch time." Some companies use "cycle time" to mean the interval at which finished units leave the whole line, so agree on definitions internally to avoid confusion.

Takt Time: The Pace Customers Need

Takt time is daily available time divided by daily required quantity. For example, with 480 minutes of available time and demand for 1,000 units, takt time is 480 × 60 ÷ 1,000 = 28.8 seconds.

Available time here means shift time minus breaks, morning meetings, and other periods when the line does not run. Kaizen Base, a Japanese improvement site, notes that takt time itself contains no allowance. To account for downtime or defects, set a separate target cycle time instead.

Asprova, a Japanese production-scheduler vendor, calculates target cycle time as available time ÷ (required quantity ÷ yield). At 98% yield, getting 600 good units means running about 612, so the target becomes about 44.1 seconds instead of 45.

Cycle Time: What Each Station Actually Takes

Cycle time is the time a station actually needs to finish one unit of work. As Keyence explains, a cycle time longer than takt means capacity falls short of the target, and a shorter one means the station can work faster than needed.

Shorter is not automatically better, though. Running far faster than takt produces piles of inventory from overproduction. The goal of line balancing is not speed for its own sake, but getting every station to the pace demand requires.

Bottleneck: The Ceiling on Output

The bottleneck is the station with the longest cycle time, and line output can never exceed what the bottleneck allows. In the earlier example, with 27,000 seconds of available time, the line makes only about 519 units a day (27,000 ÷ 52), short of the 600 required.

Listing the station times side by side reveals the bottleneck. On the floor, it usually shows up as the station with work-in-process piling up in front of it, or the one whose downstream operator is often waiting. Check both the numbers and what you see on the line to avoid picking the wrong station.

Line Balance Efficiency Formula (With a Worked Example)

Line balance efficiency, called hensei koritsu (編成効率) in Japan, puts a number on line balance. The idea is simple: what share of the operator time the line consumes actually goes into work.

Figure 3: Line Balance Efficiency Formula and Example

The denominator, bottleneck time × number of stations, is the total operator time the line actually uses.

Line balance efficiency (%) = Sum of station work times ÷ (Bottleneck time × Number of stations) × 100

Balance loss (%) = 100 − Line balance efficiency

Sum of station work times38 + 52 + 30 + 44 + 36 = 200 s
Bottleneck × stations52 s × 5 = 260 s
Line balance efficiency200 ÷ 260 × 100 ≈ 76.9%
Balance loss100 − 76.9 ≈ 23.1%

Same fictional example as Figure 1. Balance loss is the share of total operator time on the line that is spent waiting.

Balance Loss: The Share Lost to Waiting

In Figure 3, five operators each give the line 52 seconds per cycle, for 260 seconds in total. Only 200 seconds of that is work; the other 60 seconds is waiting. That 60 ÷ 260 is the 23.1% balance loss.

JIE also defines balance loss as 100 minus line balance efficiency. Since the two numbers are two sides of the same coin, pick one and use it consistently in internal reports.

Bottleneck or Takt Time in the Denominator?

Sources differ on what goes in the denominator: the bottleneck's cycle time or the takt time (pitch time). Neither is wrong. They measure different things.

Dividing by the bottleneck time shows how uneven the stations are today. Dividing by takt time shows how well the line uses operator time against the pace of demand.

Divide the Figure 3 example by the 45-second takt and you get 200 ÷ 225 = 88.9%, which looks healthy. Yet with the bottleneck above takt, the line is not meeting demand at all. In practice, first confirm the bottleneck is at or below takt, then look at efficiency.

Minimum Number of Stations

TPM Online, a Japanese maintenance and improvement site, calculates the required headcount as the sum of station cycle times ÷ standard time (takt time). For Figure 3, 200 ÷ 45 ≈ 4.44, which rounds up to a minimum of five people.

That figure is a lower bound that assumes the work can be split perfectly evenly. Cut the total to 180 seconds or less, and four people could in theory run the line. The formula makes a practical point: to reduce headcount, reduce the work itself before you reshuffle it.

What Is a Good Line Balance Efficiency? Aim for 85–90%

Recommended targets vary by source. These are the main figures from the Japanese sources behind this guide:

  • Asprova and IT Trend: 85% or higher
  • TPM Online: 90% or higher for a "reasonably well-balanced line"
  • Kaizen Base: target 90% or higher, with 80% as the minimum

On lines built around manual work, cycle times vary every cycle, so chasing 100% makes the line stop more often, not less. A practical approach is to target 85–90% and treat anything below 80% as a priority for review.

How to Improve Line Balance in Six Steps

Engineer timing an assembly task with a stopwatch

Here is how to improve a line's balance in practice. The six steps condense TPM Online's seven-step approach to reducing balance loss, among other sources, into a sequence that is easy to run on the shop floor.

Figure 4: Six Steps to Better Line Balance

Measure, make it visible, rebalance, then make it stick.

Prepare and measure
01Set the scope and targetPick a high-volume product and line; set takt time and a target efficiency
02Time each work elementBreak work down to "pick, place, fasten" and time it several times to get a representative value
03Map the precedenceDraw a precedence diagram showing which tasks must follow which
Analyze and improve
04Find the bottleneck and efficiencyDraw a yamazumi chart; quantify the bottleneck and idle time
05Rebalance the workCut work with ECRS first, then reassign work elements to stations
06Trial and standardizeRun for several days, confirm the results, and update standard work and instructions

Condensed by MONOSCOPE from the seven steps (target selection through standardization) in TPM Online's article on balance loss.

Step 1: Set the Target Line and Goal

Start by deciding which product on which line to tackle first. The usual approach is to begin with high-volume products where the payoff is largest, and on lines with many products, work down the list by volume.

Next, calculate takt time from available time and demand, and set a target line balance efficiency or headcount. Spell out the goal up front, such as "meet demand within regular hours" or "go from five people to four." That goal becomes your yardstick when you choose which fixes to try.

Step 2: Break the Work into Elements and Time Them

Timing whole stations will not tell you which tasks can move where. The key to this step is breaking the work down into work elements such as "pick up the part," "set it in the fixture," and "tighten the screws," and timing each one. Use a stopwatch time study, or record the work on video and measure the times afterward.

A series in MONOist, a Japanese engineering publication, treats the Work Factor (WF) method as its default for analyzing work. WF is a predetermined time standard (PTS) system that adds up preset time values for each motion. With stopwatch timing, observed times should be corrected by performance rating, which adjusts the operator's actual pace to standard conditions.

A single reading may happen to be fast or slow. Time each element about ten times and use a representative value with the outliers removed, so later calculations stay stable. Operators may also speed up when they know they are being timed, so explain the purpose in advance and ask them to work at their normal pace.

Step 3: Use a Precedence Diagram to See What Can Move

You cannot move a work element to any station you like. Wiring cannot start until the board is mounted, and inspection has to happen before the cover is closed. These sequence constraints limit your options.

A precedence diagram captures those constraints. Circles represent work elements, and arrows show "this task can only happen after that one." Once it is drawn, you can see at a glance which tasks can shift earlier or later.

Figure 5: Precedence Diagram and Station Assignment

As long as you follow the arrows, any task can go to any station.

Station 1: A + B + C + D = 44 sStation 2: E + F + G + H = 38 sABCDEFGH8 s12 s10 s14 s9 s4 s15 s10 s
ASet base in fixtureBMount circuit boardCScrew down boardDConnect wiringEAttach coverFApply nameplate (any time after A)GPower-on testHPack

Fictional example. Total work of 82 s ÷ 45 s takt ≈ 1.8, so at least two stations are needed. Splitting the work into 44 s and 38 s while respecting precedence gives a line balance efficiency of 82 ÷ (44 × 2) ≈ 93.2%.

Tasks with loose constraints, like applying the nameplate (F) in Figure 5, work well as balancing tasks. Knowing which tasks can float makes it much easier to even out station times later.

Step 4: Draw a Yamazumi Chart to Find the Bottleneck and Efficiency

Stack the measured times by station to build a yamazumi chart like Figure 1. If you color or divide each bar by work element, you can see exactly which tasks make a bar tall.

Draw the takt time line on the chart and check whether the bottleneck crosses it. Then calculate line balance efficiency with the formula in Figure 3 and record it as your baseline. Also note the date, product, and operators, so you can compare under the same conditions after the change.

Keep in mind that this only measures imbalance between stations. NC Network, a Japanese manufacturing portal, also describes overall line efficiency, a long-term measure based on actual results that includes daily changeovers, waiting for parts, and similar losses. If the balance looks good but actual output is poor, look for other losses such as stoppages or part shortages.

Step 5: Cut Work First, Then Rebalance

It is tempting to push bottleneck tasks straight to the next station. First, though, check whether the work itself can be reduced, using ECRS (covered in the next section). Cutting work before redistributing it shrinks the total time and opens the door to running with fewer people.

JIE calls the redistribution itself yamazumi and yamakuzushi (山積み・山崩し), literally "stacking up" and "leveling the pile." You move work elements between stations, within the precedence constraints, until every bar sits just below the takt line. Writing each element and its time on a sticky note and moving the notes around a whiteboard helps everyone involved see the same picture.

Moving tasks also moves parts and tools. Bring in the production engineers who design the process at this stage, so fixture or equipment changes can be handled quickly when needed.

Step 6: Trial and Standardize

Run the new assignment on the actual line for several days to a week. A plan that works on paper often fails in practice: part replenishment or operators still learning the new tasks can turn a different station into the new bottleneck.

Once the results hold, set the work sequence and the standard in-process stock (hyojun temochi, the minimum work-in-process kept at each station). Then update standard work sheets and work instructions. Kaizen Base notes that work only counts as standard work when all three elements are in place: takt time, work sequence, and standard in-process stock.

Fixing the Bottleneck: Four Options and ECRS

Assembly workstation with an electric screwdriver and a positioning fixture

There are four basic ways to clear a bottleneck. Figure 6 sorts the basic patterns described by Kaizen Base by their effect on headcount and when each one fits.

Figure 6: Four Ways to Clear a Bottleneck

Start with the options that keep headcount the same.

Same headcount1. Redistribute workMove some of the bottleneck's work elements to upstream or downstream stations that have idle time. Try this first.
Same headcount2. Shorten work timeSpeed up the bottleneck itself by reviewing motions, improving fixtures, changing part placement, or mechanizing.
Fewer people3. Combine stationsCut work, rebalance, and reduce the number of stations. Freed-up operators can move to other jobs.
More people4. Split the bottleneckAdd a second operator to share the bottleneck, or run a parallel station. An option when demand rises.

Organized by MONOSCOPE from the basic improvement patterns in Kaizen Base's article on line balance analysis. Option 4 raises labor costs, so use it only when options 1–3 fall short.

Use ECRS to Cut Work, in That Order

The tool for option 2, shortening work time, is ECRS. The glossary of JMA Consultants (JMAC), a Japanese management consultancy, describes it as a set of improvement principles: Eliminate, Combine, Rearrange, and Simplify, applied in that order.

In Japanese usage, "Combine" covers both merging and separating tasks, and "Rearrange" includes substituting.

Figure 7: ECRS Order and Assembly Line Examples

Work from left to right. Finding tasks you can drop has the biggest effect and costs nothing.

EEliminateCan we drop this task?Stop setting parts down and re-gripping them; assemble each part straight from the bin
CCombine (or separate)Can tasks be merged or split?Standardize on one screw type so the operator switches screwdrivers only once
RRearrange (or substitute)Can we change the order, place, or person?Move nameplate application to a downstream station with idle time
SSimplifyCan we make it easier?Add a positioning fixture so parts no longer need realigning

Order and meaning of each principle follow the JMAC glossary. The assembly line examples are fictional, written by MONOSCOPE for illustration.

Teams often jump straight to fixtures and equipment (Simplify). Asking "Do we need this task at all?" first costs less time and money and can be done right away. Motions such as a duplicate inspection check, or setting parts down after opening the bag, can often be dropped once someone looks closely.

Automating Only the Bottleneck Can Be Enough

When the bottleneck is long, repetitive work such as screw tightening or inspection, mechanization is a strong option. You do not need to automate the whole line. Handing part of the bottleneck's work to a machine can raise output for the entire line.

If you plan to use a robot that works next to people, review the safety requirements for collaborative robots before you commit.

Adding People Is the Last Resort

Splitting the bottleneck (option 4) reliably raises output, but it also raises labor costs. If demand has only risen for a short time, overtime or borrowing helpers from other lines may make more sense.

As a rule, decide on adding people only after options 1–3 still leave you above takt time. Add people first, and idle time at the other stations grows, so line balance efficiency actually falls.

Before and After: How the Numbers Change

Now apply the steps to the five-station line from Figure 1: 27,000 seconds (450 minutes) of available time, demand of 600 units, and a takt time of 45 seconds. Before the change, the bottleneck at Station 2 takes 52 seconds, and the line makes only about 519 units a day.

The first move is to cut work with ECRS. Three tasks are reduced:

  • Station 2: stop setting parts down before assembly, saving 4 s
  • Station 4: standardize the screw type, saving 6 s
  • Station 5: drop the duplicate inspection check, saving 2 s

Then the 8-second wiring-clamp task at Station 2 moves to Station 3, which had the most idle time.

Figure 8: Yamazumi Chart Before and After

Cutting 12 seconds of work and moving 8 seconds brought every station under takt time.

Before

45 s
38
52
30
44
36
12345
Total200 s
Bottleneck52 s
Efficiency76.9%
Daily output~519 units

After

45 s
38
40
38
38
34
12345
Total188 s
Bottleneck40 s
Efficiency94.0%
Daily output675 units

Fictional example. Daily output = 27,000 s of available time ÷ bottleneck time. Station 2 after the change: 52 s − 4 s (eliminated set-down) − 8 s (moved to Station 3) = 40 s.

After the change, the bottleneck drops to 40 seconds, and line balance efficiency rises from 76.9% to 94.0% (188 ÷ (40 × 5)). Daily output becomes 27,000 ÷ 40 = 675 units, so the line can now meet the 600-unit demand within regular hours.

Headcount, however, is still five. The 188-second total divided by the 45-second takt is about 4.18, so getting to four people means cutting at least 8 more seconds of work. Calculations like this turn the next goal into a concrete number.

The line now has 5 seconds of margin under takt, which absorbs normal variation in work time and minor problems. If demand stays the same, keep producing to takt time rather than using the spare capacity to run faster. That prevents overproduction.

Common Mistakes and How to Avoid Them

Team discussing station assignments with sticky notes on a drawing

Line balancing projects tend to stumble on how times are measured and how changes are sustained, more than on the math itself. Here are four common mistakes and how to avoid them.

Balancing on Average Times Only

If you load every station right up to takt based on average times, a single slow cycle will stop the line. Manual work always varies, so look at the spread as well as the average, and leave some margin.

Stations staffed by new operators or helpers from other lines run longer and vary more. Give those stations a slightly lighter load, or define a "help zone" where neighboring operators can step in. Either way, the line stops less often.

Missing Product Differences on a Mixed-Model Line

On a mixed-model line that builds several products, the bottleneck can shift from one product to the next. Balance the line around a single representative product, and one station may be swamped whenever a different product comes through.

For a mixed-model line, calculate the efficiency for each product and take the average weighted by production volume. Then use production scheduling to avoid running long-cycle products back to back. That way, the line can absorb the differences between products.

Treating It as a One-Time Fix

A balanced line does not stay balanced for long. It drifts every time something like this happens:

  • A design change adds work
  • Demand changes, and so does takt time
  • Operators change

The fix is to set a rule to review the balance whenever demand or takt time changes. Training multi-skilled operators (tanoko) who can cover several stations also makes it much easier to staff a new assignment. A skill matrix that shows who can run which station, and at what level, keeps that information in one place.

Making Headcount Reduction the Goal

Better line balance can free up people. Put that front and center from day one, though, and operators tend to stop cooperating with time studies or offering improvement ideas.

Freed-up operators usually go to help on other lines, to improvement work, or to cross-training. Frame the goal as "reduce waiting and meet demand within regular hours without strain," and the shop floor is far more likely to get on board.

Line Balance Worksheet: Set It Up in Excel

You can run the whole calculation in a simple spreadsheet. The layout below uses the Figure 1 example; replace the times with your own measurements.

CellItemExample valueExcel formula
B2:B6Work time per station (s)38, 52, 30, 44, 36Measured representative values
E1Available time per day (s)27,000Shift time minus breaks and meetings
E2Required quantity per day600Customer demand
E3Takt time (s)45=E1/E2
E4Bottleneck time (s)52=MAX(B2:B6)
E5Line balance efficiency76.9%=SUM(B2:B6)/(E4*COUNT(B2:B6))
E6Balance loss23.1%=1-E5
E7Minimum number of stations5=ROUNDUP(SUM(B2:B6)/E3,0)
E8Daily output at the bottleneck519=ROUNDDOWN(E1/E4,0)
E9Bottleneck within takt?NO=IF(E4<=E3,"YES","NO")

Format E5 and E6 as percentages. A stacked column chart built from the work-element times, with E3 added as a horizontal line, gives you a yamazumi chart from the same sheet.

Checklist and Questions for the Japanese Side

Before you compare your numbers with a Japanese plant's report, or adopt a balance proposed by a Japanese supplier, confirm the basis behind each figure.

  • Denominator: Was hensei koritsu calculated with the bottleneck time or with takt (pitch) time?
  • Available time: Which breaks, meetings, and planned stops were subtracted? Does the takt time include any allowance?
  • Target cycle time: Is there a separate target cycle time for downtime or yield? What yield was assumed?
  • Measurement method: Stopwatch, video, or a PTS system such as WF? How many readings per element, and was performance rating applied?
  • Cycle time definition: Does "cycle time" mean the time per station or the interval between finished units leaving the line?
  • Product mix: On a mixed-model line, is the figure for one product or a volume-weighted average?
  • Baseline conditions: Date, product, and operators for the before and after measurements
  • Standard work: Are the work sequence and standard in-process stock (hyojun temochi) documented for the new balance?

If you need to ask by email, questions like these usually get a clear answer:

  • Could you share the yamazumi chart with times broken down by work element?
  • In your hensei koritsu calculation, is the denominator the bottleneck time or the takt time?
  • What available time and daily quantity did you use to set takt time?
  • How many cycles did you measure for each work element, and how did you choose the representative value?
  • Which tasks are fixed by sequence, and which can move between stations?

Limits of This Guide

  • All numbers in the figures are fictional examples for explanation, not benchmarks from real lines.
  • The 85–90% target comes from Japanese improvement and software sites. It is a rule of thumb, not a standard, and the right target depends on the product, the share of manual work, and how much variation the line has.
  • Definitions of cycle time and the denominator for efficiency vary by company. Always confirm which ones a report uses.
  • The formulas here assume a single straight flow line with one operator per station. Lines with shared machines, U-shaped cells, or operators running several machines may need other methods, such as man-machine analysis.
  • Changes to fixtures, equipment, or robots involve safety requirements. Make those decisions with your production engineering, quality, and safety teams.

Summary

Key Takeaways
  • Line output is set by the bottleneck, the station with the longest work time.
  • Takt time is available time ÷ required quantity: the target pace.
  • Line balance efficiency = sum of work times ÷ (bottleneck time × number of stations). Aim for 85–90%.
  • Time each work element, map precedence, and cut work with ECRS before rebalancing.
  • Do not balance on averages alone, check product differences, and rebalance whenever takt changes.

Team leaders and line leaders can drive line balance improvements day to day. When fixtures or equipment have to change, though, they need production engineering and quality assurance involved.

FAQ

What is the line balance efficiency formula?

Line balance efficiency (%) = sum of station work times ÷ (bottleneck time × number of stations) × 100. For five stations of 38, 52, 30, 44, and 36 seconds, that is 200 ÷ (52 × 5) ≈ 76.9%. Balance loss is 100 minus that figure, or 23.1%.

What is the difference between takt time, cycle time, and the bottleneck?

Takt time is the target pace set by demand (available time ÷ required quantity). Cycle time is how long each station actually takes per unit. The bottleneck is the station with the longest cycle time, and it caps the output of the whole line.

What is a good line balance efficiency?

Targets vary by source, but 85–90% is a practical goal, and anything below 80% deserves priority review. On manual lines, aiming for 100% tends to make the line stop more often because of normal variation in work time.

Is hensei koritsu the same as line balance efficiency?

Yes, the two terms are used almost interchangeably, and JIE uses the longer name sagyo hensei koritsu (作業編成効率). Both express the sum of work times as a share of the operator time the line uses. Check whether the denominator is the bottleneck time or the takt time.

How do you calculate line balance efficiency for a mixed-model line?

Calculate the efficiency for each product, then take the average weighted by each product's production volume. Balancing around one representative product can hide a bottleneck that appears with other products, so check the difference product by product.

Sources

Found this useful? Share it

About the editor

MONOSCOPE EditorFOUNDER & EDITOR

Spent about ten years at a plant equipment maker and a plant engineering company, proposing, designing, and commissioning equipment, then moved into web marketing. Now a web consultant for B2B manufacturers, helping them explain their products and technology. Licensed in Japan as an Energy Manager and a Third-Class Chief Electrical Engineer.

Has run an engineering blog since 2017 (500+ articles) and a Japanese YouTube channel with about 20,000 subscribers. Each English guide is written from the Japanese shop-floor point of view and checked against the cited standards.