EN
2026Oct 22

Delivery Specification (Nonyu Shiyosho): What to Check

Working with JapanUpdated October 23, 202613 min read

You placed an order with a Japanese equipment maker. A few weeks later, a thick PDF arrives titled 納入仕様書 (nonyu shiyosho), and the cover asks for your approval. At first glance it looks like the quotation specification you already agreed on. It is not. Once you return it approved, the supplier can start building the equipment exactly as shown.

This guide explains what a delivery specification is, how it differs from the purchase specification, the quotation specification, and the approval drawings, and what to check before you send it back. It is written for engineers and buyers outside Japan, whether you receive a nonyu shiyosho from a Japanese supplier or need to prepare one for a Japanese customer. For return codes, stamps, and return deadlines, see our guide to approval drawings (shonin-zu).

Contents
  1. What Is a Delivery Specification (Nonyu Shiyosho)?
  2. Where It Fits: Purchase, Quotation, and Delivery Specifications
  3. What a Delivery Specification Contains
  4. How It Differs From the Quotation Specification
  5. Four Things to Check Before You Return It
  6. Delivery Specification vs. Approval Drawing vs. As-Built Drawing
  7. If You Are the Supplier: Preparing One for a Japanese Customer
  8. Delivery Specification Review Checklist
  9. Where Practice Varies
  10. FAQ
  11. Sources

What Is a Delivery Specification (Nonyu Shiyosho)?

A delivery specification is a document set that the supplier (usually the equipment maker) submits after the purchase order is placed. It describes the specifications and drawings of the equipment that will actually be delivered. The approval drawings (shonin-zu, 承認図) are the drawings within this set that the buyer is asked to approve.

Strictly speaking, drawings submitted for approval are shonin-yo-zu (承認用図), and drawings the buyer has approved and returned are shonin-zu. Fabrication starts from the returned drawings. In practice, many people call both "shonin-zu."

Names vary by company and by customer. Some buyers approve and return the whole delivery specification as one package. Others return only the drawings, as approval drawings. The purchase specification or the purchase order usually says which way your project works.

Where It Fits: Purchase, Quotation, and Delivery Specifications

On a Japanese plant project, the documents usually move in this order. The plant designer writes a purchase specification (kobai shiyosho, 購買仕様書) that states the performance the equipment must meet, based on the designer's calculations. The supplier answers with a quotation specification (mitsumori shiyosho, 見積仕様書) for equipment selected under its own design standards. After a few rounds, once both sides agree on the specifications and the price, the buyer places the order.

The delivery specification comes after that. The many document names fall into three stages: quotation, after the order, and fabrication through delivery.

Figure 1: Document names and the order they appear

The delivery specification is submitted after the order and before fabrication. Once it comes back approved, its drawings become the approval drawings.

Quotation stage
01 BuyerPurchase specification (kobai shiyosho)States the performance, conditions, and standards the equipment must meet
02 SupplierQuotation specification (mitsumori shiyosho)Specifications of the selected equipment and the scope of the quote, sent with the quotation
03 BuyerPurchase orderIssued once the specifications and price are agreed
After the order (before fabrication)
04 Supplier, for approvalDelivery specification and equipment drawingsSpecifications and detail drawings of the equipment to be delivered, submitted for approval
05 Buyer → supplierRed markups and revisionsThe buyer marks comments in red; the supplier revises and resubmits
06 Buyer, approvedReturned with approval (approval drawings)The drawings, or the whole set, returned as approved. Fabrication can start.
Fabrication through delivery
07 SupplierFabrication and inspectionBuilds to the approval drawings and inspects at the factory
08 SupplierAs-built drawings and completion documentsFinal drawings of the finished equipment, often sent with the instruction manual and test reports

Document names and stages vary by company, industry, and buyer. Some suppliers submit the delivery specification and approval drawings together; others submit only the drawings for approval.

The table below compares the three specifications. Notice how the author moves from buyer to supplier, and the purpose moves from "tell" to "agree" to "get permission to build."

Figure 2: Purchase vs. quotation vs. delivery specification

Same equipment, three documents, three different jobs.

Document
Prepared by
When
Purpose
Purchase specification
(kobai shiyosho)
Buyer (the plant designer)
When requesting quotes
Tells suppliers the required specifications, conditions, and scope of supply, so everyone quotes on the same basis
Quotation specification
(mitsumori shiyosho)
Supplier (the equipment maker)
With the quotation
Shows the specifications of the selected equipment so both sides can agree on specifications and price
Delivery specification
(nonyu shiyosho)
Supplier (the equipment maker)
After the purchase order
Shows the specifications and detail drawings of the equipment actually delivered; returning it with approval releases fabrication

Scope of supply (shosho, 所掌) means which party supplies or installs each item.

Related: Equipment Purchase Specification: Items, Checks, Template

Related: Quotation Specification (Mitsumori Shiyosho): Sample Format

What a Delivery Specification Contains

Contents depend on the equipment and on what the purchase specification asks for. A typical delivery specification includes the sections below. The right-hand column shows what the buyer checks in each one.

SectionWhat to check
Equipment specifications, load conditions, and interface detailsWhether the equipment fits the foundation and piping design
Guarantee conditionsWhether the guaranteed performance and warranty period match the contract
Assembly drawing and detail drawings of individual partsShape and dimensions; nozzle locations and orientation
Accessory specifications and detail drawingsWhether instruments, valves, and other accessories are within the scope
Performance (capacity) calculationsThe basis showing the equipment meets the performance in the purchase specification
Spare parts and consumablesQuantities, and whether they were included in the quotation
Supporting documents, such as installation and insulation proceduresWhether the work can actually be done on site

How It Differs From the Quotation Specification

The specifications are basically the same as in the quotation specification. What the delivery specification adds is content that only exists once detailed design has progressed, plus detailed drawings of the accessories. The quotation specification was for agreeing on price. The delivery specification is for permission to fabricate, so it deserves a closer look, down to the drawings.

Compare the model, materials, and accessory scope against the final revision of the quotation specification. Adjust small differences within the contract price. If a change would affect the price, discuss with the supplier whether it should be handled as an extra cost.

If you agreed on exceptions during the quotation stage, they are usually listed in a deviation list (debieshon risuto, often shortened to debikura in Japan). Check each item by its number to confirm it now appears in the delivery specification.

Here is a fictional example of a side-by-side check for a pump.

ItemQuotation specification (final rev.)Delivery specificationAction
ModelModel A-100Model A-100OK
Casing materialAs per deviation list item 3Same as deviation list item 3OK
Pressure gaugeIncludedShown, but faces the wallMark up: ask to rotate toward the walkway
Companion flanges, bolts, gasketsSupplier scopeNot listedAsk: still in supplier scope?
Spare mechanical seal1 set2 setsAsk: is the extra set included in the price?
Fictional example. Model names and items are made up for illustration.

Four Things to Check Before You Return It

When you receive a delivery specification, you review it for four main purposes. All four are points to settle before you return it with approval, by checking the contents against your own documents and with the departments involved.

Figure 3: Four checks before returning it with approval

Check each one against your own documents and with the teams who will use the equipment.

Drawings and accessoriesNozzle and instrument locations and orientation. Compare with the quotation specification and deviation list.
InterfacesLocation, type, and scope of each connection. Compare with piping, electrical, and instrument drawings.
Installation proceduresInstallation, welding, and insulation methods. Review with construction and foundation design.
Release for fabricationReturn before fabrication must start. If approval is conditional, record the conditions.

1. Assembly Drawings and Accessories

The delivery specification includes equipment drawings (nonyu-hin-zu, 納入品図): an assembly drawing showing the equipment in detail and detail drawings of accessories such as instruments. Use them to picture how the equipment will sit and be used on site, then ask for orientation changes where needed.

For example, a pressure gauge facing away from the walkway cannot be read by operators. A valve handle on the wall side is hard to operate and inspect. Send the drawings to operations and maintenance staff, not just the designer, and fewer of these problems slip through.

2. Interfaces (Toriai)

Almost every piece of equipment connects to utilities such as water, power, and steam, or to other process lines. In Japanese these connection points are called toriai (取合い). Check that each interface matches the equipment or piping it connects to.

Where equipment connects upstream or downstream, confirm the location and type of each connection, and who supplies the bolts, nuts, and gaskets. The most reliable approach is to have the piping, electrical, and instrumentation designers each check their own connections.

Figure 4: Where to check the interfaces

The interface is the boundary where the supplier's equipment meets piping and cables installed by others.

Equipment (supplier)InterfaceFlanges, boltsPiping (installer)Terminal box, cable

Check who supplies the companion flanges, gaskets, bolts, and nuts against the scope of supply agreed in the quotation specification. Check electrical terminal boxes and instrument connections the same way.

If the flange standards or pressure classes differ, the bolt holes will not line up. A wrong interface leads to rework during construction and can delay the schedule, so this is the check that needs the most care.

Related: Process vs Utility Piping: How Japanese Plants Divide Them

Related: Mating Flange (Companion Flange): Who Supplies It?

3. Installation Procedures

If the supplier is not responsible for installation, it usually submits an installation procedure (koji yoryosho, 工事要領書) covering points to watch during installation and the welding method. Review it with your construction team to confirm the work can be done without difficulty.

If there is an installation drawing or foundation drawing, check the anchor bolt locations and loads with the foundation designers. Review the insulation procedure with the insulation contractor in the same way.

Related: Equipment Loading Data for Foundations: What to Submit, When

4. Release for Fabrication

If the delivery specification and equipment drawings have no problems, you return them with approval (shonin henkyaku, also called juryo henkyaku, 受領返却). This authorizes the supplier to build the equipment to those drawings. Work back from the delivery date and make sure you return the set before fabrication has to start.

Return decisions usually fall into three types: approved, approved with conditions, and resubmit. Conditional approval lets the supplier start fabrication on the understanding that the comments will be addressed. Record which condition, who fixes it, and by when, and close the record only after the revised drawing shows the fix. If something changes after approval, the supplier shows what changed and why, and the buyer approves it again. The approval drawings also serve as the acceptance basis when you witness the factory inspection. Our approval drawing guide covers return codes, stamps, and deadlines in detail.

Related: FAT and SAT with Japanese Suppliers: Steps & Free Checklist

Delivery Specification vs. Approval Drawing vs. As-Built Drawing

Several similar names show up around the delivery specification. They differ in the project stage they belong to and the state of the equipment they describe.

Figure 5: Delivery specification, approval drawing, and as-built drawing

The full document set, the drawings that were approved, and the record of the finished equipment.

Delivery specification
(nonyu shiyosho)
Approval drawing
(shonin-zu)
As-built drawing
(kansei-zu)
When
After the order, before fabrication
Before fabrication (once approved and returned)
After fabrication and installation
Contents
Specifications, calculations, assembly and detail drawings, installation procedures
The drawings that were approved
Final drawings showing the finished condition
Approval status
Submitted for approval
Approved by the buyer
Records the finished condition, based on the approval drawings
Role
Defines and confirms what will be delivered
Record of the agreement to build it this way
Reference for operation, maintenance, and future modification

Names and boundaries vary by company and buyer. Many people also call the drawings "shonin-zu" before they are approved.

Delivery Specification vs. Approval Drawing

The delivery specification is a bundle that shows what will be delivered: specifications, calculations, and drawings. "Approval drawing" is the name for the drawings in that bundle that the buyer approves.

Approval is not always limited to drawings. A guideline from Japan's Acquisition, Technology & Logistics Agency (ATLA) defines the documents submitted for approval as including drawings, written documents, and photos. In other words, a written specification can also be the object of approval. Whether your project approves the whole delivery specification or only the drawings is set by the purchase specification or purchase order.

Delivery Specification vs. As-Built Drawing

An as-built drawing (kansei-zu, 完成図) shows the equipment as finished. In building and facility work it is also called shunko-zu (竣工図). The delivery specification and approval drawings, by contrast, are pre-fabrication documents that decide what will be built.

If dimensions or parts change during fabrication or installation, the as-built drawings reflect the result. Operation, maintenance, and future modifications rely on the as-built drawings. For equipment, they are often handed over at delivery as part of a completion document set (kansei tosho, 完成図書) with the instruction manual and test reports. For example, the common specification that Japan's Ministry of Land, Infrastructure, Transport and Tourism (MLIT) uses for purchasing telecommunications equipment requires the supplier to submit, by the end of delivery, a single delivery binder containing the instruction manual, test reports, and delivery photos.

Other Names: Nonyu-zu and Shiyo-zu

We found no definition of nonyu-zu (納入図, "delivery drawing") in the standards. In practice, treat it as roughly the same as the equipment drawings (nonyu-hin-zu) attached to a delivery specification: assembly drawings, outline drawings, and accessory details.

A shiyo-zu (仕様図, "specification drawing") puts specifications such as model, dimensions, and performance onto a drawing. For standard products, a supplier may send a single sheet combining specifications and an outline drawing under a name like nonyu shiyo-zu (納入仕様図). Whatever the name, you check the same content. Look at the cover page or transmittal to see whether the document is submitted for approval.

Japanese public-sector documents use yet another name. MLIT's common specification calls the detailed specifications and outline drawings submitted after the contract kakunin tosho (確認図書, "documents for confirmation"), which the supplier submits to obtain the agency's confirmation.

If You Are the Supplier: Preparing One for a Japanese Customer

If a Japanese customer asks you for a nonyu shiyosho, it expects the document set described above, submitted after the order and before fabrication. A few points make the review go faster.

  • Check the purchase specification or purchase order for the number of copies, the format (paper or PDF), and the submission deadline, and whether the customer approves the whole set or only the drawings.
  • Mark the cover page or transmittal clearly as submitted for approval.
  • Show where each deviation list item is reflected, by item number.
  • Keep the model, materials, and accessory scope consistent with your final quotation specification. Flag any difference that affects price instead of leaving it for the customer to find.
  • Show the scope of supply at each interface: who supplies the companion flanges, gaskets, bolts, and nuts.
  • Update the revision number and date on every resubmission so everyone can tell which version is current.
  • For changes after approval, submit a revision that shows what changed and why, and wait for approval before building that part.

Delivery Specification Review Checklist

Use this list when you review a delivery specification from a Japanese supplier. If you are the supplier, it shows what your Japanese customer is likely to check.

CheckCompare against / ask
Model, materials, and accessory scopeFinal revision of the quotation specification
Every deviation list item reflectedDeviation list, item by item
Guaranteed performance and warranty periodContract and purchase specification
Performance calculations meet the required dutyPurchase specification
Nozzle and instrument locations and orientationPlant layout; operations and maintenance staff
Connection location, size, type, and standard at each interfacePiping, electrical, and instrument drawings
Who supplies companion flanges, gaskets, bolts, and nutsScope of supply in the quotation specification
Anchor bolt locations and loadsFoundation design
Installation, welding, and insulation procedures workable on siteConstruction team; insulation contractor
Spare parts and consumables: quantities and price coverageQuotation
Changes that affect priceDiscuss whether to treat them as an extra cost
Return dateFabrication start date worked back from delivery
Conditions on a conditional approvalRecord what, who, and by when

Questions to Ask the Japanese Supplier

  • Is this document submitted for approval, or for reference only?
  • Do you need the whole delivery specification approved, or only the drawings?
  • Which revision of the quotation specification is this based on?
  • Where is each deviation list item reflected in this submission?
  • Who supplies the companion flanges, gaskets, bolts, and nuts at each nozzle?
  • Does any change from the quotation affect the price or the delivery date?
  • When do you need our return to keep the fabrication schedule?
  • What will the completion documents include, and how many copies will you deliver?

Where Practice Varies

  • Document names and stages differ by company, industry, and buyer. Many people call the drawings "shonin-zu" even before approval.
  • Whether the whole set or only the drawings is approved depends on the purchase specification or purchase order.
  • The contents listed here reflect plant equipment. Standard catalog products may come with only a single specification drawing.
  • Return decision labels vary by company, and return deadlines are set in the purchase specification or purchase order. Confirm them for every project.

FAQ

Is a konyu shiyosho the same as a kobai shiyosho?

In most cases, yes. Konyu shiyosho (購入仕様書) and kobai shiyosho (購買仕様書) are two names for the same purchase specification: the buyer's document stating the performance, conditions, and standards the equipment must meet.

Is a nonyu shiyosho the same as a nohin shiyosho?

Both names are sometimes used for a document showing the specifications of delivered goods, and there is no fixed distinction between them. Use whichever name appears in the contract or in the customer's own documents.

How many copies of a delivery specification are required, and in what format?

The purchase specification or purchase order usually sets the number of copies, the format (paper or PDF), and the deadline. MLIT's common specification for telecommunications equipment, for example, leaves the number of copies of delivery documents to the project's special specification. Update the revision number and date on every resubmission so the latest version is clear.

What happens if something changes after approval?

The supplier submits a revision showing what changed and why, and builds that part only after it is approved again. ATLA's guideline calls this revised submission a "document for change approval" (henko shonin-yo tosho). If the buyer requested the change, discuss any extra cost and the impact on the delivery date as well.

Sources

Found this useful? Share it

About the editor

MONOSCOPE EditorFOUNDER & EDITOR

Spent about ten years at a plant equipment maker and a plant engineering company, proposing, designing, and commissioning equipment, then moved into web marketing. Now a web consultant for B2B manufacturers, helping them explain their products and technology. Licensed in Japan as an Energy Manager and a Third-Class Chief Electrical Engineer.

Has run an engineering blog since 2017 (500+ articles) and a Japanese YouTube channel with about 20,000 subscribers. Each English guide is written from the Japanese shop-floor point of view and checked against the cited standards.

MoreRelated

More guides

All guides